Debris Collection, Crushing and Public Road Paving North of Wadi Gaza
One work chain that lifts debris, crushes it and returns it to the field as public road layers
The Gaza Society for Sustainable Agriculture and Friendly Environment (SAFE) is implementing the project in partnership with the United Nations Development Programme / Programme of Assistance to the Palestinian People (UNDP/PAPP), funded by the Government of Norway through the Norwegian Ministry of Foreign Affairs. The project is valued at USD 710,000. It targets the collection of 80,000 tons of debris, the crushing and processing of 80,000 tons, and public road paving works over 60,000 m². It is one component of SAFE's work on Emergency Debris Management in the Gaza Strip.
Background and Need
When the war stops, its rubble stays in the road. North of Wadi Gaza, debris blocks public roads, slowing residents' movement and delaying ambulances, relief trucks and services on their way into neighbourhoods.
Lifting the debris is not enough on its own. The quantities removed need processing rather than a new dump, the cleared roads need a surface fit for traffic, and construction materials are scarce and hard to bring into the Strip. The project therefore links the three needs in one chain: it collects the debris, crushes and processes it, then uses the crushed output to pave public roads.
Main Objective
The project's main objective is clearing debris from the target areas north of Wadi Gaza and turning it into material for paving public roads, reopening those roads to residents and services.
Key Activities and Interventions
The Project in Numbers
The quantity targeted for crushing equals the quantity targeted for collection: the project does not move debris from one place to another; it processes what it collects.
SAFE's Role
SAFE implements the project as UNDP's implementing partner. It put the works out to a publicly advertised competitive tender for contractors classified by the Palestinian Contractors Union. Its engineers supervise collection, haulage, crushing and paving on site every day, and every truckload is documented on a weighbridge card.
Expected Impact
More broadly, the project prepares the ground for what follows: no reconstruction without cleared land, and no return without passable roads.
We invite our partners and donors to build on this model and scale it; every ton recycled lifts a burden from a neighbourhood and paves a road to it.