Emergency Rehabilitation for Partially Damaged Housing Units for Displaced Families in the Gaza Strip
An emergency response combining self-help and contractor-led repairs to bring displaced families back to their homes
When a home is partially damaged, it still stands, but the damage keeps the family from returning to it and living there safely. Across the Gaza Strip, affected and displaced families still rely on shelter centres while their homes remain in this condition, although what those homes need is emergency, non-structural repair, not reconstruction.
In response, the United Nations Development Programme / Programme of Assistance to the Palestinian People (UNDP/PAPP) is implementing the Emergency Rehabilitation for Partially Damaged Housing Units for Displaced Families in the Gaza Strip project, in cooperation with the Gaza Society for Sustainable Agriculture and Friendly Environment (SAFE) as implementing partner. Two donors fund the project: the Sheikh Abdullah Al Nouri Charity Society funds the rehabilitation of 200 housing units, and the Italian Agency for Development Cooperation funds the rehabilitation of 210 housing units. In total, the project targets 410 housing units and runs from 20 September 2026 to 19 April 2027.
Project Objective
The overall objective is enabling affected and displaced families to return to their homes and live there in safe and dignified conditions. The project does so through emergency, non-structural repairs to partially damaged housing units.
Target Groups and Selection Criteria
The project targets affected and displaced families whose housing units were partially damaged in four Gaza City neighbourhoods: Al-Daraj, the Old City, Al-Zaytoun and Al-Sabra. It benefits 410 housing units.
Candidate units are assessed in the field, then ranked neighbourhood by neighbourhood on an assessment weighted 60% social and 40% engineering. A unit is selected only if:
Under the Self-Help modality, the beneficiary must also be able to take charge of the works and give written consent. Units under this modality are approved jointly by UNDP, SAFE and the relevant parties.
Implementation Approach
The project uses an implementation model that combines two modalities: Self-Help and Contractor-Led. The targeted housing units are divided between them as follows:
Key Interventions and Activities
Works under both modalities are emergency, non-structural repairs, delivered differently in each.
Under the Self-Help modality:
Under the Contractor-Led modality:
SAFE's Role
Four SAFE field teams, each made up of an engineer and a female social researcher, visit and assess the candidate units. SAFE's engineering staff also supervise and follow up the repair works that beneficiaries carry out under the Self-Help modality. SAFE performs both roles as implementing partner to the project.
Expected Results and Impact
On completion, the project is expected to deliver:
We call upon our partners and donors to build upon this model and expand it; every rehabilitated housing unit enables families to live in their homes with dignity.